Site readiness before steel arrives
A checklist worth working through before the first delivery, because every item on it stops the crane if it is missed.
Steel that arrives on a site which is not ready is not progress. It is a storage problem with a delivery charge attached. The items below are the ones that most often stop a lift.
Foundations and bolts
- Concrete cured sufficiently to take load
- Holding-down bolts set to position and level, surveyed and recorded
- Bolt threads protected and clean — damaged threads stop erection cold
- Base levels confirmed, packing and grout arrangements agreed
Access
- Haul route able to take a loaded delivery vehicle, in the weather expected
- Crane standing positions confirmed, with ground bearing capacity checked
- Overhead services identified, and exclusion zones agreed where they cannot be moved
- Turning and reversing space for deliveries, without blocking other trades
Lay-down
Somewhere to put steel that is within crane reach, level, drained, and clear of other trades. Steel stacked in the wrong order costs a rehandle for every member.
Documentation
- Approved erection drawings on site, current revision
- Lift plan and method statement accepted
- Temporary works design for stability during erection
- Permits in place, and the site's own induction arranged
The one that catches people
Holding-down bolt position. Bolts set even slightly out of tolerance mean a column that will not sit, and the remedy — oversized plates, or worse — is a design decision taken under time pressure. A survey before the steel is loaded is inexpensive insurance.